Final Intended Use Plan for the New York State Drinking Water State Revolving Fund

Project Readiness List

The Project Readiness List for this IUP begins with projects that have received a written confirmation letter that they qualify for financial hardship and are determined to be ready. These projects are identified by 'H' in the column labeled "score." Phased or segmented projects are assigned 2000 points in addition to their total project ranking system score. Projects that have closed on a short-term financing are assigned 1000 points in addition to their total project ranking system score and are identified by 'NOTE: Short-Term Loan Closed' in the column labeled "project cost."